PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
"It does not apply to this *particular* project". It did not say that "it does not apply to this project anymore". If the risk was an error >> option B If the risk is outdated >> option C
Correct answer for me is C. You should not remove a risk form the risk register but close it instead
C is correct as you need to make all stakeholders aware that it is no longer a risk.