PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- External risks originate outside the organization. Regulatory changes and weather conditions are external factors beyond the project's control. Design complexity and technology are technical risks, resource availability and funding are typically organizational risks, and schedule/communication issues are project management risks.