PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Effective risk governance requires clear role definition and executive support. The PM should ensure the risk management plan clearly defines expectations for functional manager participation, and leverage the sponsor to communicate these expectations. Proceeding without input misses important perspectives, immediate CEO escalation is premature, and canceling workshops abandons risk management. Clear governance plus sponsor engagement is the professional approach.