PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
A contingency reserve is a budget allocated for unforeseen risks that may arise during a project. It is an essential part of risk management and helps ensure that the project can continue smoothly even if unexpected issues occur.
A is correct
KU RISKS, KNOWN UNKNOWN WE USE CONTIGENCY RESERVES