PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Agile risk management emphasizes addressing high-risk items early ("risk-driven iterations") to gain knowledge and reduce uncertainty while there is still time to adapt. Detailed plans (A) fail in uncertain environments. Time buffers (C) address schedule risk but not technical risk. Outsourcing (D) may transfer risk but doesn't reduce overall project uncertainty.