PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
A. Immediate termination: While cutting losses might seem prudent, it might prematurely discard potential value from the delivered work and may not consider alternative solutions. C. Bring in experts: While expertise can be helpful, it might be resource-intensive and incur additional costs when the remaining time and budget are limited. D. Release without the feature: This could significantly impact the product's functionality and value proposition, potentially damaging user experience and brand reputation.
Vote B, there is no additional time to do more sprints since its at the end of the project.
When a critical feature is not functioning as expected and the project is at a high risk of failure, the product owner should review possible options and make an informed decision based on the delivered business value. This could involve evaluating the potential impact of the failing feature on the overall value of the product and deciding whether it's better to cut losses by terminating the project or by making adjustments to salvage the value that has been delivered.