Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Swarming—having multiple team members collaborate to complete work items before starting new ones—addresses the imbalance by having developers help with testing when coding is done. This promotes knowledge sharing and reduces bottlenecks. Extending sprints (A) delays feedback. Hiring (B) is a long-term solution that doesn't address immediate flow issues. Reducing testing (D) compromises quality.