CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: B. Contingency plan ✅ Here's why: Since the project is scheduled during peak hurricane season, the project manager should prepare a contingency plan to: Identify potential risks (e.g., hurricane impact). Develop actions to take if those risks occur. Ensure the project can continue or minimize damage/delays if a hurricane hits. A contingency plan is created before a risk occurs and lays out alternative actions to manage or mitigate the impact.
A Contingency Plan is indeed the recommended action when a project faces potential risks like hurricane season during its implementation . A contingency plan allows for proactive management and preparation for potential adverse effects of such risks, ensuring the project's ability to adapt or recover swiftly should the risks materialize.