CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: B. Resize the resource utilization to reflect current needs ✅ Here's why: If the PM sees that the Infrastructure as a Service (IaaS) usage is only at 20% capacity, it indicates over-provisioning — paying for more resources than needed. To optimize costs and efficiency, the PM should: Resize or scale down the resources to better match actual usage. This avoids unnecessary expenses while still meeting the project's needs.
i think its B
Just makes the most sense.