CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: ✅ A. Make an impact assessment. (Most Voted and Correct) Here's why: When a delay is identified (in this case, IT equipment delivery), the first step should be to: Assess the impact of the delay on the overall project schedule, budget, scope, and resources. Understand how this delay affects milestones, dependencies, and deliverables. Gather accurate information to inform decision-making and communication with stakeholders.
An issue has arisen, perform an impact assessment of the problem and make changes accordingly.
Think like a bureaucrat lol