CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. Statement of work (SOW) ✅ Here's why: When a project manager identifies the need to procure goods and/or services, the next logical document to prepare is the Statement of Work (SOW). The SOW: Clearly defines the products, services, or results to be delivered. Outlines deliverables, timelines, and performance criteria. Becomes part of the procurement documentation to solicit vendors.
I initially thought B. But after some research, RFI comes after the SOW is created in order to request more information based on the specific needs outlined in the SOW. Understand the procurement process
You don't request for information after making a choice.