CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: B. To avoid a negative impact on other software functionalities Explanation: Change control is a critical aspect of software project management and software development lifecycle (SDLC). One of its key goals is to maintain the integrity and stability of the system. When changes are made without proper approval or review, there's a significant risk that the change could introduce bugs, conflicts, or unexpected consequences in other parts of the software — known as regression.
Per AI source... B. To avoid a negative impact on other software functionalities. Obtaining approval for changes in software is a critical step in the change management process. It ensures that any modifications are thoroughly reviewed and assessed for potential impacts on existing functionalities. The approval process typically involves stakeholders who can identify possible conflicts or issues that the change might introduce, thereby minimizing the risk of adverse effects on the system’s operation.