CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Transfer Explanation: When a project manager buys an extended warranty, they are shifting the financial risk of potential server failures or repairs to another party — in this case, the warranty provider (usually the vendor or insurer). This is a classic example of risk transfer, where the impact of the risk is handled by someone else, typically through insurance, warranties, or outsourcing.