CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. Begin executing the rollback plan. Explanation: The project sponsor has set a strict downtime limit of 3 hours, and at 2.5 hours the validation is only 70% complete with issues. To avoid exceeding the downtime and potentially causing bigger problems, the project manager should initiate the rollback plan to restore the system to its last stable state