CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: D. Start with no financial plan and justify each new expense. Explanation: Zero-based budgeting requires that every expense must be justified from scratch, rather than using previous budgets as a baseline. It starts at zero and builds the budget based on current needs.