CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Milestone Explanation: A milestone chart highlights major accomplishments or key events in a project timeline. It is ideal for showing progress on important deliverables or phases.
Milestone = Major accomplishment
A Milestone Chart