CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: B. Transfer Explanation: When the project team outsources part of the work due to lack of internal resources, they are essentially shifting the risk to a third party (the external vendor). This is a classic example of risk transfer.