CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. The project manager did not complete the project closure phase Explanation: Even though the project was released into production, the continued project-related work suggests the project has not been formally closed. This points to an incomplete project closure phase.