CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. Agile Here's why: When the requirements are not well defined, and the goal is to quickly deliver a minimum viable product (MVP), the best approach is to use a flexible, iterative methodology — which is exactly what Agile provides.