CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: D. Release schedule Explanation: The Release Schedule outlines when the new system or product will be deployed or activated in production. Since this impacts the organization and stakeholders, it typically requires approval from the project sponsor to ensure alignment with business goals and readiness.
At the point where testing is complete and the system is ready for production, the deployment plan outlines how and when the system will be activated. This is a critical transition point, and approval from the project sponsor is often required to ensure: All stakeholder expectations are met, Business risks are managed, The organization is ready for the change. The sponsor's approval gives the green light for production deployment.
Release = available for use Deployment = move to live environment