CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: B. RACI Explanation: Once the project manager has identified all the resources (people, teams, groups), the next step is to clarify who is responsible, accountable, consulted, and informed for each task or deliverable. The RACI matrix is the best tool for this because it: Clearly defines roles and responsibilities Maps each task or deliverable to resource roles using: R = Responsible (who does the work) A = Accountable (who owns the task/outcome) C = Consulted (who provides input) I = Informed (who needs to be kept updated)
Responsible, Accountable, Consulted, Informed. The big one is R.
B. RACI - This stands for Responsible, Accountable, Consulted, and Informed. It's a matrix used to clarify the roles and responsibilities in a particular process or set of tasks. In the context of project management, a RACI matrix shows the relationships between tasks and the individuals or teams assigned to them, indicating who is responsible for performing the task, who is accountable for the task's completion, who needs to be consulted, and who should be informed about the task's progress and results. Given the options and the need to identify which resources are responsible for which tasks, the RACI matrix (option B) is the most suitable choice.