CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Allocate resources Explanation: The project manager has already done these key steps: Validated constraints Outlined task durations and phases Confirmed proper sequencing and flow What typically comes next to complete the project schedule is: ➡️ Allocate resources to the scheduled tasks.
Developing a schedule in Project+: • Identify Tasks • Estimate Durations • Sequence Tasks • Resource Requirements • Allocate Resources • Create Schedule • Validate • Set Baselines • Document/Communicate • Monitor/Update
Chat GPT says D. I think its reasoning is solid. During the scheduling phase, the project manager may review the planned schedule, adjust task durations, sequences, dependencies, and resource assignments as necessary to ensure feasibility and alignment with project objectives. Establishing baselines during the scheduling phase involves setting the schedule baseline, which includes freezing the schedule to reflect the agreed-upon plan against which actual progress will be measured. Therefore, even though establishing baselines is typically associated with the planning phase, it's also an essential activity during the scheduling phase to complete and formalize the project schedule before moving into execution and monitoring phases.