CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: ✅ B. Identify and evaluate risks Here's why: When a project is large, complex, and irreversible once started, the most critical first step is to identify and evaluate risks. This ensures: Potential threats to budget, timeline, scope, or quality are discovered early High-impact risks can be mitigated or planned for in advance Contingency planning is built into the project plan Because the project cannot be cancelled once initiated, early risk management is vital to prevent costly failures or surprises
The answer is B. Identify and evaluate risks. Option C, establishing change management procedures, is also important, but it is not as important as identifying and evaluating risks. Change management procedures can be put in place after the risks have been identified and evaluated. A large, complex project that is new to the organization is likely to have a lot of risks. These risks could impact the project's budget, schedule, or scope. By identifying and evaluating these risks early on, the project manager can develop mitigation plans to minimize their impact.
it says the project is VERY NEW to the org. couldnt that mean unforseen changes