CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: B. Work with the business analyst to document the new epic. Here's why: In Scrum, the Product Owner is responsible for managing the Product Backlog, including adding or reprioritizing items as needed. When the Product Owner requests adding new scope, the Scrum Master does not act as a gatekeeper to reject or approve changes — instead, their role is to facilitate the Scrum process and ensure the team works effectively within that framework
It's coming from the Product Owner, no need for a change request.
If someone in the organization wants a change in the Product Backlog, they need to discuss this with the Product Owner and try to convince them. But at the end of the day, the Product Owner makes the decision.