The best choice here is: C. Advise that a change request would need to be approved. Why? The original budget and scope include only a specific number of workstations. Adding extra workstations is a change to the project scope and budget. The project manager must follow formal change control procedures. This means the request should be documented as a change request and then evaluated for impacts on cost, schedule, and resources before approval.
Letting the dep manager know that this isnt a decision that you can make yourself is the first thing you would want to do here.
A change was made and a change request is needed.