Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Critical Path is the longest sequence of activities in a project schedule that determines the shortest possible time to complete the project. Float (or Slack) is the amount of time an activity can be delayed without delaying the project's overall completion date.