Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A program risk threshold defines the level of risk exposure that is acceptable to key stakeholders. It guides risk response decisions by establishing when risks require active responses versus acceptance, and when risks must be escalated to governance. Exam tip: Risk thresholds are set by stakeholders and the governance board—they define the boundary between acceptable and unacceptable risk exposure.