ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
An increase in residual risk: This is critical information for senior management. Residual risk is the risk that remains after controls are applied, and an increase in this risk could signify potential issues that might require strategic decisions or additional resources. Senior management needs to be aware of changes in residual risk to make informed decisions about resource allocation, risk tolerance, and strategic planning.
The answer is C. An increase in residual risk. Residual risk is the risk that remains after controls have been implemented. It is important to report on increases in residual risk to senior management because it indicates that the organization's controls may not be effective in mitigating risks.