ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
No matter how I analyze this, it is C.
C. Of risk trigger. The alarm serves as a risk trigger because it indicates that the machine's temperature is approaching the critical threshold (450°F) where the windings may burn. A risk trigger is an event or condition that signals a potential risk is about to occur, prompting a predefined response A. Risk indicator: While the alarm could indirectly indicate risk, its primary role is to activate a response (trigger), not just monitor. B. Risk identification: The alarm doesn’t identify the risk (overheating is already known); it reacts to it. D. Risk response: The shutdown is the response; the alarm triggers that response.
The risk trigger is the temperature reaching 430°F, not the alarm itself. In this scenario, the alarm acts as a risk indicator because it alerts the team when the temperature reaches 430°F, signaling that the machine is getting close to the dangerous threshold (450°F).