ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Monitoring and Controlling is used to track risks, monitor risk triggers, reassess existing risks, and implement contingency or fallback plans if necessary. But the initial implementation of the risk response (like adding security, changing vendors, buying insurance) happens during Executing.
A is the correct answer Monitor and Control Risk is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project