Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The power/interest grid classifies stakeholders into four quadrants: High Power/High Interest = Manage Closely; High Power/Low Interest = Keep Satisfied; Low Power/High Interest = Keep Informed; Low Power/Low Interest = Monitor. A stakeholder with high power but low interest should be kept satisfied because while they have the authority to impact the project, they are not actively engaged. If they become dissatisfied, they may use their power to negatively affect the project. Overloading them with information may cause annoyance, while ignoring them is risky.