Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
WAIT god damn AI thats not right, it starts at week 6 and takes 5 weeks, thats 10 weeks not 11 Sorry!!
11 weeks: Activity A starts and takes one week. Activity B starts at the same time as Activity A and takes three weeks. So, at the end of Week 3, both A and B are complete. Activity C follows A and B. Since A and B are complete at the end of Week 3, C starts in Week 4 and takes two weeks. So, at the end of Week 5, Activity C is complete. Activity D follows C. Since C is complete at the end of Week 5, D starts in Week 6 and takes five weeks. So, at the end of Week 11, Activity D is complete. Therefore, the total time to complete the project is 11 weeks.
C. Planning out the critical path is B>C>D for a total time of 10 weeks