Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
B. Define Activities When developing the project schedule, the process that involves decomposition and rolling wave planning techniques is "Define Activities." In this process, the project manager breaks down the project work into smaller, more manageable components or activities. Decomposition is the technique of subdividing project deliverables and project work into smaller, more manageable parts.
B is correct answer
Rolling Wave Planning is one of the techniques in the ‘Define Activities’ process under Project Time Management.