Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Why the other options are incorrect: A. Expert judgment, data analysis, and interpersonal and team skills → These are general techniques used in many processes, but expert judgment and interpersonal skills are more relevant during planning or identification, not primarily for monitoring. C. Expert judgment, audits, and decision making → “Decision making” is not a primary tool for monitoring risks. Expert judgment may be used, but it's not the core technique here. D. Meetings, data gathering, and expert judgment → “Data gathering” (like interviews) is used more during risk identification or planning, not in the monitoring phase.
Can' use "expert judgment" when it comes to risk.
B for sure