- A make-or-buy analysis is used to determine whether specific work can best be accomplished by the project team (make) or should be purchased from an outside source (buy). The analysis considers direct and indirect costs, internal capability, risk, schedule impact, and strategic factors. It is a key tool in the Plan Procurement Management process and helps determine which project needs can best be met through procurement.