Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Resource requirements is an output of Estimate Activity resources process and Project team assignments is an output of Acquire resources process
C for sure
C for sure
Team assessments happen in develop team, as an output. Therefore they are not an input to a previous process in the planning process.