- A one-time effort with a unique purpose (reconfiguring for a new product line) and a defined completion date meets the PMI definition of a project - it is temporary and creates a unique result. Routine replacement of worn parts and scheduled annual maintenance are examples of operations because they are repetitive and ongoing. The personnel involved do not determine whether something is a project or operations; it is the nature of the work that matters.