Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
Question 18 of 190
Free Preview · 190 of 631 · questions 1–190 of 631 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A one-time effort with a unique purpose (reconfiguring for a new product line) and a defined completion date meets the PMI definition of a project - it is temporary and creates a unique result. Routine replacement of worn parts and scheduled annual maintenance are examples of operations because they are repetitive and ongoing. The personnel involved do not determine whether something is a project or operations; it is the nature of the work that matters.