Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Resource leveling adjusts the project schedule to resolve resource conflicts or overallocation by delaying activities until resources are available. This often extends the critical path and increases the project duration. Resource smoothing, by contrast, adjusts activities within their float so the schedule end date is not affected. Fast tracking and crashing are schedule compression techniques, not resource optimization techniques.