Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A RACI chart is the most common type of Responsibility Assignment Matrix. RACI stands for Responsible (does the work), Accountable (ultimately answerable, only one per activity), Consulted (provides input, two-way communication), and Informed (kept updated, one-way communication). The RACI chart ensures every work package has clear ownership and prevents confusion about roles.