Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The Closing phase involves finalizing all activities, obtaining formal acceptance of deliverables, conducting procurement audits, archiving project documents, and capturing lessons learned. Developing the WBS is a Planning activity, identifying stakeholders is an Initiating activity, and establishing baselines is a Planning activity. Proper closing ensures that organizational knowledge is preserved and contracts are formally closed out, preventing future disputes.