- The Closing phase involves finalizing all activities, obtaining formal acceptance of deliverables, conducting procurement audits, archiving project documents, and capturing lessons learned. Developing the WBS is a Planning activity, identifying stakeholders is an Initiating activity, and establishing baselines is a Planning activity. Proper closing ensures that organizational knowledge is preserved and contracts are formally closed out, preventing future disputes.