Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The work package is the lowest level of the WBS. It represents a deliverable or project work component at the most granular level where cost and duration can be reliably estimated and managed. Activities are further decompositions of work packages but appear in the activity list, not in the WBS itself.