- The Scrum Guide 2020 states that a Sprint could be cancelled if the Sprint Goal becomes obsolete, and that only the Product Owner has the authority to cancel the Sprint. The 2020 Guide no longer details the older (2017) procedure for reviewing Done items and re-estimating incomplete work; the essential rule is PO-only cancellation when the Sprint Goal is obsolete.