During the implementation of an item in the Sprint Backlog, a conflict arises between team members about what work is needed to make the item 'done'. Some say it is a part of the Definition of Done and others say it isn't. Steven, the Scrum Master, observes a debate forming and members beginning to take sides. What is the best action for Steven to take?
Select one answer.
Marked answer: C
Community Discussion
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Chose C1
The SM role s to facilitate and coach team along with helping the team remove impediments.