Professional Scrum Master I (PSM I) · Scrum
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Gonna go against the grain and say D, since only the developers can change the sprint backlog. Any impediments are also raised during dailies and discussed with the team. No one person can make changes without discussing it as a team.
Also since new work needs to be estimated first.
B Sprint Backlog It is a highly visible, real-time picture of the work that the Developers plan to ...