Professional Scrum with Kanban I (PSK I) · Scrum
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- An SLE has two parts: an elapsed-time period and a probability. '85% of items finish in 8 days or less' is a textbook SLE format. The team derives it from the historical distribution of cycle times.