Professional Scrum with Kanban I (PSK I) · Scrum
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The SLE is a forecast of how long it should take a given work item to flow from started to finished. It has two parts: an elapsed-time period and a probability. For example, '85% of work items will finish in 8 days or less.' Scrum Teams use historical cycle time data to derive an SLE.