Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Withdraw/avoid involves retreating from the conflict or postponing the issue. While generally not recommended for significant conflicts, it can be appropriate when the conflict is minor, when emotions are running too high for productive discussion, or when more important issues need attention first.