A team member made an unauthorized scope change. The PM should first understand the impact on scope, schedule, cost, quality, and other areas before deciding what action to take. A ❌ — Removing the change immediately may be premature. B ❌ — Adding resources doesn't address the unauthorized change. C ❌ — Documentation should not be updated before the change is evaluated and approved. D ✅ — Assess the impact first, then follow the change control process. 👉 Answer: D